Dunga Substation
Energy
Information
Project Description
Construction of a 132/33 kV substation at Dunga. Project identified as a candidate for EUD support, with the hope of enabling participation from a European contractor
Planned location
Zanzibar
Financing Partners
- EU
Implementing Partners
Not specified
EU or EU MS supported?
Yes
EU private sector interest?
High interest from EU companies as EPC contracts and TA
Main opportunities for EU private sector (e.g. engineering services, works, equipment supply, digital solutions, PPP opportunities, technical assistance, etc.)
EPC, TA, supplier of equipment, Digital Solutions such as SCADA and STATCOM
Allocated amount
EU Investment Grant € 13 000 000
Status/Procurement plan
Feasibility Study under procurement by ZECO
Implementation period
2027-2028
Type of Project
EU Government Project