Dunga Substation

Dunga Substation

Energy

Information

Project Description

Construction of a 132/33 kV substation at Dunga. Project identified as a candidate for EUD support, with the hope of enabling participation from a European contractor

Planned location

Zanzibar

Financing Partners

  • EU

Implementing Partners

Not specified

EU or EU MS supported?

Yes

EU private sector interest?

High interest from EU companies as EPC contracts and TA

Main opportunities for EU private sector (e.g. engineering services, works, equipment supply, digital solutions, PPP opportunities, technical assistance, etc.)

EPC, TA, supplier of equipment, Digital Solutions such as SCADA and STATCOM

Allocated amount

EU Investment Grant € 13 000 000

Status/Procurement plan

Feasibility Study under procurement by ZECO

Implementation period

2027-2028

Type of Project
EU Government Project